I set an environment of Project Sever 2007 with 5 user. 1 Project Manager
and 4 Team Members. I'd created a project plan and assign the differents
resources to differents tasks and upload.

When I login to PWA with Project Manager user and click Task Center appear
all tasks assigned to the Team Members and when I login with Team Member
user dont appear any task. I don't know why happen this.

Please, any help.
 
G

Gary L. Chefetz [MVP]

Richiee:

Did you publish the assignments? This is accessed from the file menu in this
version.
 
P

Paul Conroy

PS2007 has a concept of assignment owners which the PM will probably be. This
allows other users to track the progress of tasks assigned to other staff
members. The default assignment owner is a property of each enterprise user.
 