E
Erkki Piipari
Greetings.
Has anybody encountered this use case (MSP 2002 Pro) ?
- Task is 100 % complete
- Build team, a new resource
- Assign him to this task, which has several other
resources
=> for every working day of the task a whole day (7,5
hours of work and actual work is calculated (taken from
duration)
What is the proper order of making corrections in MSP
(Change work, remaining work, delete faulty actuals...)?
The calculation gives some curious results.
Final stage although is to republish and overwrite actuals.
Much obliged - as usual
PS I love deadlines. I like the whooshing sound they make
as they fly by. (Douglas Admas)
Erkki
Has anybody encountered this use case (MSP 2002 Pro) ?
- Task is 100 % complete
- Build team, a new resource
- Assign him to this task, which has several other
resources
=> for every working day of the task a whole day (7,5
hours of work and actual work is calculated (taken from
duration)
What is the proper order of making corrections in MSP
(Change work, remaining work, delete faulty actuals...)?
The calculation gives some curious results.
Final stage although is to republish and overwrite actuals.
Much obliged - as usual
PS I love deadlines. I like the whooshing sound they make
as they fly by. (Douglas Admas)
Erkki