Assigning task on vacation day for a specific scneario(for SF depe

S

Satya

Hi,
We have two tasks with task1 has *SF* dependency on task2 as follows
Task Id | Task Name | Duration |Start |Finish| Dependency | Resource Names
1 | Task1 | 1 day | April 20, 2010 8:00 AM | April
21, 2010 9:00 AM | 2SF | R1
2 | Task2 | 2 days | April 21, 2010 9:00 AM | April
23, 2010 9:00 PM| |R2
R1 is on vacation on 21st April
MPP displays the end of Task1 as April 21, 2010 9:00 PM
Issue: As R1 is on vacation on 21st, expectation is that the Task1 should
finish on 20th Apr not on 21st Apr.
How can we resolve this issue in MS Project 2007?
Regards
Satya
 
J

Jan De Messemaeker

Hi,

Your dependency tells task 1 not to finish before Task 2 starts. That's what
Project does for you.
The task can by no means end on April 20 because of this dependency.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 