M
Mufasa
I'm a MS Project newbie so this is probably a stupid question.
How can I have multiple tasks that aren't dependent on each other not appear
on the same day?
Here's what I've done - I've created multiple tasks and assigned a duration
to them. I then assigned them all to the same resource (myself) and they are
all starting on the same day. The tasks aren't dependent on each other so
there is no need to set predecessors but I do want to have it that I only
work on a single task on any given day. Is the only way to do this to set
predecessors or is the a way to have the system automatically not allow me
to assigned the same resource to multiple tasks on a given day ?
Don't know if it makes a difference but I'm using Project 2003.
TIA - Jeff.
How can I have multiple tasks that aren't dependent on each other not appear
on the same day?
Here's what I've done - I've created multiple tasks and assigned a duration
to them. I then assigned them all to the same resource (myself) and they are
all starting on the same day. The tasks aren't dependent on each other so
there is no need to set predecessors but I do want to have it that I only
work on a single task on any given day. Is the only way to do this to set
predecessors or is the a way to have the system automatically not allow me
to assigned the same resource to multiple tasks on a given day ?
Don't know if it makes a difference but I'm using Project 2003.
TIA - Jeff.