Assignment and Resource Group

G

Gérard DUCOURET

Hello,

How can I read with VBA, for each assignment of each task, the name of the
resource "Group"
Thanks for help

Gérard Ducouret
 
J

Jan De Messemaeker

See my in long reply in the French NG

atask.resourcegroup
atask.resources(x).group
activeproject.resources(atask.assignments(x).resourceid).group
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
Project Management Consultancy
Prom+ade BVBA