Assignment Duration

S

Steve Scott

In Resource Usage View I am trying to show the duration of the assigment...is
this essentially the same as the work value?

Thanks in Advance
 
M

Mike Glen

Hi Steve,

Welcome to this Microsoft Project newsgroup :)

Yes - provided you have only one resource assigned to that task.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 