Assignment Timephased / Non-Timephased Concept

G

Gustavo Holloway

Hi,

Could someone give me an explanation on the concept of Assignment Timephased
/ Non-Timephased at Project Server 2007?

Regards
 
M

Marc Soester [MVP]

Gustavo, generally timephased means that you have a time dimension in your
cube ( which allows you to report by time), unlike the non timephased.

Assignment timephased give you the capabillity to report on resources that
are assigned to projects for a given time.

hope this makes sence
 
G

Gustavo Holloway

Makes all sense. I was wondering that but needed some confirmation just to be
sure. Thanks A Lot!!
 
Top