Assingment View - change unit of summary tasks

H

Hans Wurst

Hi there,

we are using project with project server and I'v a little problem.

If I open an assingment view (grouped by RSP) the summary is shown in hours.
No problem - I change via Option => schedule (???) to show work in days.
That's all right and it's working.

But it's not working at my boss' PC. He changes this option and and the unit
in the summary keeps the same - hours.

Any idea how to solve it? F9 does also not help. :-(

best reagrds

Michael
 