Attaching Documents to Tasks

K

kmcmee

We are able to attach documents to projects but not to
tasks. What settings do I need to change in Project
Server 2002 to allow documents to be attached to tasks?

Thanks. kmcmee
 
C

cnewlon

We discovered that failure to set the SharePoint server as
a trusted site causes this problem.
 