Auto Calculate not working

J

Jeff Tunney

Hi,

I have noticed that after having created some Enterprise fields with
formulas in them, I always have to do an F9 to get the fields to populate,
even though Auto Calcualtion is turned on. This is tedious and
frustrating - WHY don't these Enterprise fields calcualte automatically ?

Thanks

Jeff
 
D

Dale Howard

Jeff --

Many of us have noticed this, too, I suspect. Immediately after I create a
new enteprise field with a formula and/or an indicator, and place the new
field in a new custom Table, I have to recalculate the project to get the
values to work. However, from that point forward, the values in those new
enterprise fields recalculate automatically whenever the project is
recalculated.

Are you needing to recalculate repeatedly, or is your situation like mine
where you have to recalculate only immediately after you create the
enterprise field? Let me know.
 