S
Steve
Is there a MSP process to cause 1 or more projects flate filed into one
overall program flat file to relate their resources to the default task
allocation of a resource(e.g. Program level or flat file master) in a manner
that when the resource assignment allocation changes in a related project
that is physically located in the Program MSP flat file (mpp), that the
master resource allocation is automaticially reflects the change?
Here is the example:
Resource #1 is an IT operations resource who is allocated for the month at
160 hours. This same resource is also working one or more projects to some
level of effort e.g. 40 hours each. Each of these projects are contained in
the flat file mpp with the program. When the allocation changes for Resource
#1 at the related project level to now be more e.g. 50% instead of 25% how
can I cause the operations task allocation to be reduced automatically be the
amount of the change?
Is this at all possible in MSP 2003 Standard? If so how? Thank You!
overall program flat file to relate their resources to the default task
allocation of a resource(e.g. Program level or flat file master) in a manner
that when the resource assignment allocation changes in a related project
that is physically located in the Program MSP flat file (mpp), that the
master resource allocation is automaticially reflects the change?
Here is the example:
Resource #1 is an IT operations resource who is allocated for the month at
160 hours. This same resource is also working one or more projects to some
level of effort e.g. 40 hours each. Each of these projects are contained in
the flat file mpp with the program. When the allocation changes for Resource
#1 at the related project level to now be more e.g. 50% instead of 25% how
can I cause the operations task allocation to be reduced automatically be the
amount of the change?
Is this at all possible in MSP 2003 Standard? If so how? Thank You!