Greg
I created a project plan using generic resources. After publishing the plan
to Project Server 2007, I replaced the generic resources with actual people.
However, all of the tasks are assigned to me and show up in My Tasks (I am
one of the resources assigned to the project), but not in the "My Tasks" for
the other resources. When I published the project with the actual people
resources, I had expected the tasks to be assigned to the people and show up
in My Tasks for each. What do I need to do?
Second question...I have also created a project workspace for this project.
I noticed that the workspace has a tasks list. Can the tasks from the
project plan fill in the project workspace task list automatically?
to Project Server 2007, I replaced the generic resources with actual people.
However, all of the tasks are assigned to me and show up in My Tasks (I am
one of the resources assigned to the project), but not in the "My Tasks" for
the other resources. When I published the project with the actual people
resources, I had expected the tasks to be assigned to the people and show up
in My Tasks for each. What do I need to do?
Second question...I have also created a project workspace for this project.
I noticed that the workspace has a tasks list. Can the tasks from the
project plan fill in the project workspace task list automatically?