W
wendyB
I have been working with a very large schedule comprising of sections of
several discrete projects with interdependencies among these sub-projects and
I am now at the point where the project owners would like to have the
"master" split into several smaller sized schedules and so that each one
could manage their own schedule. Assuming that publishing these
sub-schedules into MS Project Enterprise isn't going to eliminate the need
for cross-linking the dependencies among the what would be resultant
sub-schedules (correct me if I'm wrong), is there a way to automate the
splitting up of a master into several individual .mpp files with
cross-dependencies without losing the precedessor/successor information?
Thanks in advance.
several discrete projects with interdependencies among these sub-projects and
I am now at the point where the project owners would like to have the
"master" split into several smaller sized schedules and so that each one
could manage their own schedule. Assuming that publishing these
sub-schedules into MS Project Enterprise isn't going to eliminate the need
for cross-linking the dependencies among the what would be resultant
sub-schedules (correct me if I'm wrong), is there a way to automate the
splitting up of a master into several individual .mpp files with
cross-dependencies without losing the precedessor/successor information?
Thanks in advance.