Hello:
I have some doubts related to the availability views
inside the resource centre.
I have one resource who has an enterprise calendar of 9
hours a day for the whole year.
He has some tasks assigned for some time. In the
availability view I just can see his available hours in
the graph until middle of june, and I don't understand why
this happens, if he's supposed to be available all time
while he is in my enterprise. At the same time his
available hours are 0 in previous days (I understand that
is fine since for days that have passed he shouldn't have
available time), but this stops 10 days before today's
date, that is he is available to work on some previous
days.
I can guess that this availability is calculated in
dependance of publicated proyects, but I don't understand
fully how. Could someone help?
Thanks
José
I have some doubts related to the availability views
inside the resource centre.
I have one resource who has an enterprise calendar of 9
hours a day for the whole year.
He has some tasks assigned for some time. In the
availability view I just can see his available hours in
the graph until middle of june, and I don't understand why
this happens, if he's supposed to be available all time
while he is in my enterprise. At the same time his
available hours are 0 in previous days (I understand that
is fine since for days that have passed he shouldn't have
available time), but this stops 10 days before today's
date, that is he is available to work on some previous
days.
I can guess that this availability is calculated in
dependance of publicated proyects, but I don't understand
fully how. Could someone help?
Thanks
José