Availability Hours Showing Double

C

cecile

One of my resources is showing double hours for
availability. We have over a hundred resources in the
enterprise pool and this is the only one I am having this
problem with.

Thanks in advance.
 
R

Ryan

Cecile

It may be easier for you to remove this resource from the Enterprise Resource Pool and then
re-add him or her

You will need to delete this resource from the SQL Tables

Here is the code : execute MSP_DROP_ENT_RES @PROJ_ID ='', @RES_UID = 39

Note: # 396 is just an example.... Go to the Resource tab in Web access and find out what the persons resource # is and then replace the 396 with whatever the resouces # is...

Please note: Send an email out to all your project managers letting them know that this is going to take place because they will need to possibly delete and re-add this user to their plan..

Thanks

Support @ http:\\www.enterpriseprojectconsulting.co

Online & telephone support available
 
S

Skoegahom

Cecile,

Are they by chance assigned to summary tasks in a
project? That is one way to double someone's time...
Admin projects are another way to double time if you are
not careful.

Skoe...
 