average work

M

Michael Vestel

I'd like to have a column where i display the AVERAGE percent work per
resource. is there a way to do this.



I want it to take the work and divide it by the length. for example, if i
have 20 hours per week on a project, have it display 50% in a resource usage
view. I can even do it manually and just take the column "work" and divide it
by the duration...



This is my third time posting the question, but its not showing up...
 
J

Jan De Messemaeker

Hi,

Tfis is a different question than the one(s) you posted before!
In Resource Usage right-click on the right part of the view, select detail
styles.
Look for Percent Allocation, click show.
There you are.
HTH


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top