cario said:
Why the BAC, BCWS, BCWP value are 0.00? Are these fields are to be filled
manually.
many thanks....
cario,
Did you set a baseline? If not, then those earned value metrics will
show as 0.00. Also, have you entered progress with respect to a status
date? Is calculation set for "automatic"? All of these things can affect
whether earned value metrics are calculated.
Earned value fields (e.g. BAC, BCWS, BCWP) are calculated automatically
by Project. They cannot be entered manually by the user.
John
Project MVP