Click Project - Project Information... In the Project Information dialog
box, click the Schedule From drop-down list and select Project Finish Date.
Set a date for the Finish Date of your project and click OK. MS Project
will now tell you when you SHOULD have started work on your project. It may
be in the past! HA! Hope this little bit helps.
Ask a Question
Want to reply to this thread or ask your own question?
You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.