Back scheduling

D

David Staps

How can I back schedule from a project completion date to
arrive at a start date, using offset days for each of the
tasks?
 
D

Dale Howard

David --

Click Project - Project Information... In the Project Information dialog
box, click the Schedule From drop-down list and select Project Finish Date.
Set a date for the Finish Date of your project and click OK. MS Project
will now tell you when you SHOULD have started work on your project. It may
be in the past! HA! Hope this little bit helps.
 