Base Calendars

D

dave

Hi, my resources are in 2 seperate development centres, 1 in UK and 1 in
Isreal.
The UK resources are ok on a standard calendar, however the Israeli ones
work a different week [ Sunday - Thursday ] this was ok in MSP as I could set
up additional base calendars - how do I do the same in MSP Server ?
 
M

mark.everett

With Admin rights, start Project Pro, then use Tools > Enterprise
Options > Open Enterprise Global.

With Enterprise Global Open, go to Tools > Change Working Time. Click
New at the bottom and name the Calendar. Define the workdays,
holidays, etc and click OK to save it.

Save the Enterprise Global and exit all the way out of Project.

Restart Project, then Tools > Enterprise Options > Open Enterprise
Resource Pool. Each resource using that calendar needs to have that
calendar set for the Resource Calendar. Save and exit.

For each project, you will need to select that calendar in the Project
Information dialog box.

Hope this helps,
Mark Everett | PMP
www.quantumpm.com
 
D

dave

Mark,
Thanks for that.

I've already set a number of calendars up in MSP on my 'local' global
template, however these aren't viable from MSP Server - is there any way to
'copy' these accross ?

Thanks
 