I have added an entriprise project cost field called Budget Cost. I wanted the user define the value here. This would increase if more budget is allocated to a project.

Is it possible to baseline this enterprise field. Is is possible for me to keep track of the changes done to this field

Cna anyone suggest me

cheer
arun.
 
D

Dale Howard [MVP]

Arun --

The only task fields baselined by Microsoft Project are the Start, Finish,
Duration, Cost, and Work fields. If you wanted to baseline the Budget Cost
field, you could probably create an additional cost field and then use a
macro to capture the values in the Budget Cost field. Hope this helps.

--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"


Arun said:
Hi,

I have added an entriprise project cost field called Budget Cost. I wanted
the user define the value here. This would increase if more budget is
allocated to a project.
Is it possible to baseline this enterprise field. Is is possible for me to
keep track of the changes done to this field.
 
Top