KingKikapu;4585536 said:
Is there any way to baseline a MATERIAL resource cost on a task, bu
keep the original baseline start/finish dates (even if the dates hav
since changed!)?
Thank you,
One way is to:
1. Capture the current Start and Finish dates
2. Then change the start and finish to the old baseline dates
3. Change the units to the new value so that the cost equals what yo
want the new baseline cost to be.
4. Set the baseline on the selected task and be sure to check the bo
to roll-up to summaries.
5. Change the Start and Finish dates back to the original values
If this task has an actual start or if there is predecessors that driv
the start date, you will have to record what the actuals are and remov
the link before doing the above steps. Then reset those values