I understand that Finish Variance is the difference between baseline and the
current scheduled finish date. Now, my question is that I want to always
make sure that I am using the most current baseline. In other words, I could
save Baseline1, Baseline2, and Baseline3 and I would then want to use
Baseline3. However, the next project could have one baseline and the next
project could have five. How do I account for that possibility?