C
CQ
I understand that finish variance is the difference between baseline finish
date and the current scheduled finish date. However, I do I make sure that I
am using the most recent baseline? In other words, on Project A, I might
have Baseline1, Baseline2 and Baseline 3 but on Project B I have only one
Baseline and then on Project C I have five baselines. How can I account for
this?
date and the current scheduled finish date. However, I do I make sure that I
am using the most recent baseline? In other words, on Project A, I might
have Baseline1, Baseline2 and Baseline 3 but on Project B I have only one
Baseline and then on Project C I have five baselines. How can I account for
this?