I am using Project 2002. If I have a baseline set on my entire
project, then need to re-baseline a few tasks, what is happening when
I save the selected tasks' new baseline information into the original
baseline? Should I save into one of the baseline1 through 10 fields?
Although I get a prompt that the original baseline has been used, it
doesn't seem to have any obvious effect when I save the selected tasks
into the original baseline. The non-selected tasks seem to keep their
original baseline values, and the EV data appears intact.
I started thinking that I might be overwriting the entire project
baseline with the selected tasks only. Instead, it appears that I am
only overwriting the selected tasks in the original baseline. Is this
correct?
Thanks,
Scott
project, then need to re-baseline a few tasks, what is happening when
I save the selected tasks' new baseline information into the original
baseline? Should I save into one of the baseline1 through 10 fields?
Although I get a prompt that the original baseline has been used, it
doesn't seem to have any obvious effect when I save the selected tasks
into the original baseline. The non-selected tasks seem to keep their
original baseline values, and the EV data appears intact.
I started thinking that I might be overwriting the entire project
baseline with the selected tasks only. Instead, it appears that I am
only overwriting the selected tasks in the original baseline. Is this
correct?
Thanks,
Scott