J
J Burford Fields
Project Server 2003 SP2.
I'm looking at a project's baseline cost numbers. The numbers for
tasks are fine. However, the lines roll up, and then the summaries
roll up to a phase total that is not mathmatically correct.
Is this the sort of thing that forcing a binary rebuild will fix?
JB Fields
I'm looking at a project's baseline cost numbers. The numbers for
tasks are fine. However, the lines roll up, and then the summaries
roll up to a phase total that is not mathmatically correct.
Is this the sort of thing that forcing a binary rebuild will fix?
JB Fields