Hi,

Can someone explain me as to how many Baseline Costs can be saved in Project
2007? Is there a upper limit to it?

Thanks in advance to all who would respond to my question.
 
R

Rob Schneider

For you, I just looked in Project 2007 in a couple of places.

: in Help: searched for "baseline" and see the article "Create or update
a baseline or an interim plan" and it say "you can save up to 10 interim
plans".

: Menu: Tools/Tracking/Set Baseline and I noticed in the pull down list
for Set Interim Plan that there are 10 available. With the Baseline,
that means you can store up to 11 at any point.

--rms

www.rmschneider.com
 
M

Mike Glen

Hi Aravind,

Welcome to this Microsoft Project newsgroup :)

If you insert a column, scroll down the pick list to see that you can select
Baseline1 to Baseline10 fields. That's it. However, there's nothing to
stop you archiving the project as many times as you like with 10 baselines
in each.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top