Baseline Start and Finish Dates different in PWA vs. MSP

J

jdsmith1

The published project shows a baseline different than what the developers see
on the timeline sheet. The project has been repulblished (Assignments, etc.).
??
 
D

Dale Howard [MVP]

jdsmith1 --

Did you click Collaborate - Publish - Republish Assignments specifically?
If not, try it and let us know the results.
 
J

jdsmith1

Dale,

Thank you. Yes I did that; however, I found the answer just as you
responded. The problem was when I selected Tools/custome/Published and moved
the fields from left to right, I moved Baseline Start before I moved Baseline
Finsh to the right side. After doing that, I went back in and Republished and
it worked. Cannot move them out of order and I saw that one statement on
another forum question. :(

Jerry
 
D

Dale Howard [MVP]

jdsmith1 --

If you are using Project Server 2003, your Project Server administrator can
set the standard order in the Timesheet view. In Project Server 2002, each
resource must drag the columns manually to the desired location. Hope this
helps.
 