Baseline Work Actual for the group task

N

nhcox

Hi

I have group task that consists from many subtasks. Accidently I
deleted field Baseline Work for the group task. How to make it again to
sum Baseline Work fields of all subtasks?
 
J

Jan De Messemaeker

Hi,
(In the newer versions of Project)
select the summary task
Tools
Tracking
Save Baseline
For selected tasks
check from subtaks into selected summary task
OK

HTH
 
N

nhcox

The problem is that this option instead of updating the summary task
baseline by the sum of baselines of the subtasks, it copies over from
work to baseline work for subtasks and then summs the value. This means
I have no way to compare with baseline work, as it was planned before.
 