S
Steve B
Hi,
Why would I get different results when I get the Baseline Work Hours
from the following views:
1) Gantt View(Insert Baseline Work hours)group by Resource. Baseline
Work for a particular resource is 256 hours.
2)Resource Usage view (Insert Baseline Work hours) Baseline Work for
the same resource is 3200 hours.
This project uses a Resource Pool. With or without the Resource Pool
open I get the same results.
Thanks in advance for any help,
Steve B
Why would I get different results when I get the Baseline Work Hours
from the following views:
1) Gantt View(Insert Baseline Work hours)group by Resource. Baseline
Work for a particular resource is 256 hours.
2)Resource Usage view (Insert Baseline Work hours) Baseline Work for
the same resource is 3200 hours.
This project uses a Resource Pool. With or without the Resource Pool
open I get the same results.
Thanks in advance for any help,
Steve B