Baseline work values missing

T

Todd A

I would like to compare my actual work on each task to my original estimates.
I saved two baselines. One when the initial project plan was completed and
a second one after a major update to the plan. I have followed the
directions in the help files which say to look at the Gantt chart and
selected the Work view (View>>Table>>Work). However, the Baseline column
shows zeros for all tasks. Am I missing a step here?

I appreciate any help that can be offered! :)
 
J

Jeanders

Since you saved the baseline twice previously you may have used one of the
other baseline groups (i.e. baseline1-10). Try double clicking on the
Baseline column header (in the standard Work table) and in the column
definition box change the fieldname to Baseline1 Work... then Baseline2
Work... etc etc... you may find the values you are looking for in one of
these other fields.
 
T

Todd A

Thank you so much for your help!! That was exactly it. I had spend an hour
trying to find anything about this in the help files, knowledgebase and
forums. This comparison is a huge help for evaluating how well I am
estimating (I have room to improve it looks like :) Thanks again :)

Todd
 