T
Todd A
I would like to compare my actual work on each task to my original estimates.
I saved two baselines. One when the initial project plan was completed and
a second one after a major update to the plan. I have followed the
directions in the help files which say to look at the Gantt chart and
selected the Work view (View>>Table>>Work). However, the Baseline column
shows zeros for all tasks. Am I missing a step here?
I appreciate any help that can be offered!