baseline

G

Girija

Once we publish the project, baseline as well after resources update can we
rebaseline? Does it have anyimpact anywhere?
 
D

Dale Howard [MVP]

Girija --

Yes, you can always rebaseline a project at any time. The consequence is
that you lose all variance up to that point and resets all variance back to
0. Hope this helps.
 
G

Girija

Hi Dale,

Yes it was quite helpful. So can we also baseline the project and then
republish?

Thanks

Girija
 
D

Dale Howard [MVP]

Girija --

Yes, that is correct.




Girija said:
Hi Dale,

Yes it was quite helpful. So can we also baseline the project and then
republish?

Thanks

Girija
 