A
Astroboy
We have imported some schedules into our newly installed Project 2003
EPM tool. Some of these projects had baselines saved and that baseline
data has transferred. However, none of our baseline-driven project
scoring is working for these projects.
Further, when I open one of these projects in Project Pro, I can see
data in the Baseline columns. However, when I go into
Tools>Tracking>Save Baseline, it appears as if there is no Baseline
saved.
These projects were originally created in Project 2000, 2002 and 2003 -
we had quite a hodgepodge before we installed the EPM tool.
How can we get our baseline data to drive our scoring? We don't want to
rebaseline the projects as we'll lose important stuff.
Thanks in advance for any help you can provide!
EPM tool. Some of these projects had baselines saved and that baseline
data has transferred. However, none of our baseline-driven project
scoring is working for these projects.
Further, when I open one of these projects in Project Pro, I can see
data in the Baseline columns. However, when I go into
Tools>Tracking>Save Baseline, it appears as if there is no Baseline
saved.
These projects were originally created in Project 2000, 2002 and 2003 -
we had quite a hodgepodge before we installed the EPM tool.
How can we get our baseline data to drive our scoring? We don't want to
rebaseline the projects as we'll lose important stuff.
Thanks in advance for any help you can provide!