What do you mean by "updated baselines?" Baselines aren't updated unless
you force them by saving a fresh version and you really shouldn't do that
unless the project changes materially after you have begun work on it.
Multiple baselines are there to preserve an audit trail when the project is
changed. The baseline itself is static, preserving the orginal estimates on
the project for later comparison with the actuals and under normal
circumstances should be saved once before work starts and then locked down
and not updated after that point. If you do update it, you lose all your
variance information
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit
http://www.mvps.org/project/faqs.htm for the FAQs