Baselinework column show no information

T

TVH

I have been modify by adding a baselinework column into timsheet view, but
this column show no information in PWA Tasks/timesheet view.

Thanks for your help
 
J

Jim

TVH,

The Baseline Work column is only populated if you "Baseline" the project.
To do this, Select Tools:Tracking:Save Baseline. Be sure that "Entire
Project" is selected before updating. This will copy all the information in
the current time and effort fields (i.e. Start, Finish, Work, Cost , etc.)
into the respective columns under Baseline (i.e. Baseline Start, Baseline
Finish, Baseline Work, Baseline Cost, etc.). Baselining your projects
provides a starting point to measure progress, change management, etc.

Hope this helps.

Thanks,

Jim
 