B
Bert
How would you properly baseline a project when the overall task duration will
be larger than the actual work any task requires. (Note: Many resource's
other job demands will seldom allow tasks to be started when scheduled. 1 to
5+ day delay)
To avoid overallocation of resources will require project managers to set
unrealistic baslines for their respective projects. (Note: Senior Management
wants all projects to be baselined.)
Can anyone provide some sage advice or best practices used to overcome this
problem?
Thanks
Bert
be larger than the actual work any task requires. (Note: Many resource's
other job demands will seldom allow tasks to be started when scheduled. 1 to
5+ day delay)
To avoid overallocation of resources will require project managers to set
unrealistic baslines for their respective projects. (Note: Senior Management
wants all projects to be baselined.)
Can anyone provide some sage advice or best practices used to overcome this
problem?
Thanks
Bert