L
lynne baker
Hi all
(Today is one of those days where I think I shouldn't be allowed to be
in charge of a kettle, let alone an IT project...)
OK, so I have a development manager who tells me his list of tasks
will take a certain number of man days to complete, and that he has 4
full time resources assigned to them.
Ergo..a task estimated to take 4 man days should finish 1 in day, if
all 4 of them are working on it at the same time.
So, why does his plan still show that 4 days will elapse before the
task is completed?
I've no doubt this is something really basic...
Any suggestions gratefully received.
Many thanks
lynne
(Today is one of those days where I think I shouldn't be allowed to be
in charge of a kettle, let alone an IT project...)
OK, so I have a development manager who tells me his list of tasks
will take a certain number of man days to complete, and that he has 4
full time resources assigned to them.
Ergo..a task estimated to take 4 man days should finish 1 in day, if
all 4 of them are working on it at the same time.
So, why does his plan still show that 4 days will elapse before the
task is completed?
I've no doubt this is something really basic...
Any suggestions gratefully received.
Many thanks
lynne