Hi All
Project Server 2002: just before switching Master Plan publishing off,
we erroneously published a Master Plan containing 11 inserted Planning
Objects, with all its/their assignments. Now of course, PWA users are
getting double assignments, one from the original Planning Object, one
from the Master Plan.
(And yes, I know allowing Master Plans is suboptimal, but well...
business rules.)
Is there a way to delete all these assignments from the PWA database
(MSP_WEB, if I'm not mistaken) at once?
Thanks in advance for any hints
François
Project Server 2002: just before switching Master Plan publishing off,
we erroneously published a Master Plan containing 11 inserted Planning
Objects, with all its/their assignments. Now of course, PWA users are
getting double assignments, one from the original Planning Object, one
from the Master Plan.
(And yes, I know allowing Master Plans is suboptimal, but well...
business rules.)
Is there a way to delete all these assignments from the PWA database
(MSP_WEB, if I'm not mistaken) at once?
Thanks in advance for any hints
François