Batches of new tasks in PS 2007

D

Dan E.

We have several groups looking to submit new tasks to existing
projects in our system. The default way to do this is to go to My
Tasks in PWA and click New>Task, then fill out the task information,
then submit it. Is there a way to submit new tasks in a datasheet
view so a user does not have to click on the same items for each task
and submit them one by one?
 
M

Marc Soester [MVP]

Hi dan,

Unfortunatly there is not out of the box functionality which allows you to
enter new tasks on a datasheet level, but generally there is no reason why
you cant custom develop this functionality. Project Server certainly allow
you to develop the functionality.

Hope this helps
 