R
roadkill
I have a Project schedule where the BCWP in incorrect on only a few tasks.
But if I change the %complete and then change it back to the original value,
the BCWP becomes correct. If you have seen this, do you know the cause and
how to fix it (short of changing %complete as described above, of course)?
But if I change the %complete and then change it back to the original value,
the BCWP becomes correct. If you have seen this, do you know the cause and
how to fix it (short of changing %complete as described above, of course)?