V
Vic
Hi,
The BCWS and BCWP, and ACWP fields are all giving me the entire Baseline
amount or zero depending on the Status Date and the Actual Hours Entered.
I have the EV Method set to % Complete (I tried Physical % Complete but lost
all SPI & CPI numbers). So I'm back to % Complete.
So here's the example - Task A has 80 hours baselined at $140/hr for the
resource. Baseline Cost correctly shows $11,200 for the task. The task
starts on 2/11/2010 and runs through 3/11/2010 due to a 2 week vacation.
When I change the Current Date and Status Date to today. The BCWS is giving
me the full $11,200. I'm thinking it should be about $4,480 since the entire
task/cost isn't scheduled to be done until March. When I enter the 16 hours
spent on the task (via the Resource View and Actual Work) the BCWP & ACWP
both go directly to $11,200. Again I'm thinking they should read in the
$4,480 range.
Am I missing a setting somewhere? Your help is much appreciated
The BCWS and BCWP, and ACWP fields are all giving me the entire Baseline
amount or zero depending on the Status Date and the Actual Hours Entered.
I have the EV Method set to % Complete (I tried Physical % Complete but lost
all SPI & CPI numbers). So I'm back to % Complete.
So here's the example - Task A has 80 hours baselined at $140/hr for the
resource. Baseline Cost correctly shows $11,200 for the task. The task
starts on 2/11/2010 and runs through 3/11/2010 due to a 2 week vacation.
When I change the Current Date and Status Date to today. The BCWS is giving
me the full $11,200. I'm thinking it should be about $4,480 since the entire
task/cost isn't scheduled to be done until March. When I enter the 16 hours
spent on the task (via the Resource View and Actual Work) the BCWP & ACWP
both go directly to $11,200. Again I'm thinking they should read in the
$4,480 range.
Am I missing a setting somewhere? Your help is much appreciated