N
nova85
I am using MSP 2000. I have a task that has a March 1, 2009 start date and
April 30 end date. I added the actual cost for this task before it was
baselined. So the actual cost = baseline cost. The status date is set to
April 30. The task is 100% complete. Shouldn't the BCWP equal the baseline
cost? It does not.
April 30 end date. I added the actual cost for this task before it was
baselined. So the actual cost = baseline cost. The status date is set to
April 30. The task is 100% complete. Shouldn't the BCWP equal the baseline
cost? It does not.