BCWP showing up under Resource, but not task name

E

Evan

Hey all,

I'm having a problem getting my BCWP values to show up. I am looking at the
Task usage view at Actual Work and BCWP values. For each resource, there is
a BCWP in the row. But those values are not rolling up to the task name row.
I'm thinking this is a bug but can't find any info on it.

Thank you for any help you can give.
 
J

JulieS

Hi Evan,

Check Tools>Options, Calculation tab. Is "Updating Task status updates
resource status" selected? With that option unchecked, I can replicate
exactly what you report -- a BCWP for assignment (represented by resource
name in the Task Usage View), but zero for BCWP at the task row.

Hope this helps. Let us know how you get along.

Julie
 