Evan
Hey all,
I'm having a problem getting my BCWP values to show up. I am looking at the
Task usage view at Actual Work and BCWP values. For each resource, there is
a BCWP in the row. But those values are not rolling up to the task name row.
I'm thinking this is a bug but can't find any info on it.
Thank you for any help you can give.
I'm having a problem getting my BCWP values to show up. I am looking at the
Task usage view at Actual Work and BCWP values. For each resource, there is
a BCWP in the row. But those values are not rolling up to the task name row.
I'm thinking this is a bug but can't find any info on it.
Thank you for any help you can give.