BCWP Zeroed out

D

David

Is there any reason why BCWP would be zeroed out for all tasks? I have a
3000 line schedule and for some reason, all the data in the BCWP is all zero.

David
 
J

Joe

Each resource needs to have a rate associated with it, which is defined in
the Resource Sheet and you must baseline the plan.
 