J
Julia
Hi,
I'm investigating BCWS, BCWP, ACWP values in MS Project 2002. I've
found that all three values are calculated with different logic for
assignments, tasks and resources.
After my investigation I can understand how BCWS, BCWP, ACWP for
assignments and tasks are calculated, however I can not understand the
logic of BCWS and BCWP calculations for resources.
Does anybody have an idea how MS Project calculates BCWS, BCWP values
for resources? Especially if project has task where planned resource
(saved in baseline) was changed when the actual work was started.
Any help will be appreciated.
Julia Zaika.
I'm investigating BCWS, BCWP, ACWP values in MS Project 2002. I've
found that all three values are calculated with different logic for
assignments, tasks and resources.
After my investigation I can understand how BCWS, BCWP, ACWP for
assignments and tasks are calculated, however I can not understand the
logic of BCWS and BCWP calculations for resources.
Does anybody have an idea how MS Project calculates BCWS, BCWP values
for resources? Especially if project has task where planned resource
(saved in baseline) was changed when the actual work was started.
Any help will be appreciated.
Julia Zaika.