The PMO of the organization published a project plan on MSP 2003.
He now wants the project manager to receive the updates from the various
team members. The project manager republished the tasks from her computer,
and the PMO still receives some of the updates. Any suggestions?
Thanks,
Daniel
 
J

JeffT

The PM needs to Collaborate=>Publish=>Republish Assignments and then check
the "Become the owner" box
 