I think so.
Double-click the assignment mine in either Task Usage or Resource Usage view
and in Assignment Information select Bell as a work contour
HTH
I could be wrong, I have been before, but I think the question is about how
to generate the cumulative work "S" curve rather than a bell contour.
Let' see what he says.