J
Jack L. Calkins, PMP
Environment:
Functional organization (i.e. not a matrix or projectized organization).
Specifically, one team, let's call them the production team, manages their
own resources but provide services to multiple design teams using a shared
resource pool who receives work assignments from the Production Team manager.
MS Project 2007 clients with file shares. [We are waiting on Project Server
2007 implementation].
Goals:
1. Allow overall organization PM, that's me, to rollup status of all
in-flight projects.
2. Allow design team PMs to schedule and level their resources but not
impact the scheduling of the Production team resources even though they are
in their projects activity network.
3. Similarly allow the production team manager to schedule and level his
resources without automatically impacting all design teams schedules.
4. Have the overall organization, PMO (that's me), consolidate all the
projects and resources and do modelling and impact analysis without altering
the "production" project files.
Question: What's the "best technical and process approach" to do this
without Project Server?
My Assumptions:
1. The "best" approach for structuring MS Project to meet the above
objectives is to split the tasks among multiple files such that the design
team tasks and resources are in one file (which could consist of multiple
concurrent "joint" projects) and the production teams task and resources are
in another file (which will ultimately consist of multiple production tasks
for the various Design teams).
2. Is there a technical solution to "fencing" off the impact of the design
teams schedule changes from the production team resources?
3. If #2 above is no. Then what process approach is appropriate?
4. From an overall approach any issues with linking all 23 concurrent
sub-projects and 180 resources into a master project file for status
reporting purposes?
5. Any way to save a copy of the master organization portfolio (~3000 tasks
and 180 projects) if it's a link of the multiple subprojects to have just the
PMO (that's me) be able to play with resource levelling and modelling the
impact of changes to the portfolios across the design and production teams
without impacting their team assignments?
Thanks in advance for your assistance!
Jack
Functional organization (i.e. not a matrix or projectized organization).
Specifically, one team, let's call them the production team, manages their
own resources but provide services to multiple design teams using a shared
resource pool who receives work assignments from the Production Team manager.
MS Project 2007 clients with file shares. [We are waiting on Project Server
2007 implementation].
Goals:
1. Allow overall organization PM, that's me, to rollup status of all
in-flight projects.
2. Allow design team PMs to schedule and level their resources but not
impact the scheduling of the Production team resources even though they are
in their projects activity network.
3. Similarly allow the production team manager to schedule and level his
resources without automatically impacting all design teams schedules.
4. Have the overall organization, PMO (that's me), consolidate all the
projects and resources and do modelling and impact analysis without altering
the "production" project files.
Question: What's the "best technical and process approach" to do this
without Project Server?
My Assumptions:
1. The "best" approach for structuring MS Project to meet the above
objectives is to split the tasks among multiple files such that the design
team tasks and resources are in one file (which could consist of multiple
concurrent "joint" projects) and the production teams task and resources are
in another file (which will ultimately consist of multiple production tasks
for the various Design teams).
2. Is there a technical solution to "fencing" off the impact of the design
teams schedule changes from the production team resources?
3. If #2 above is no. Then what process approach is appropriate?
4. From an overall approach any issues with linking all 23 concurrent
sub-projects and 180 resources into a master project file for status
reporting purposes?
5. Any way to save a copy of the master organization portfolio (~3000 tasks
and 180 projects) if it's a link of the multiple subprojects to have just the
PMO (that's me) be able to play with resource levelling and modelling the
impact of changes to the portfolios across the design and production teams
without impacting their team assignments?
Thanks in advance for your assistance!
Jack