B
Bunmi
Hello all,
Just a quick question (I hope)...I'm just starting out at
this, and I want to know what you guys recommend. My
team develops custom software. We will be using Project
2003 and PWA. My question is:
1.
I'm a little confused which one I want as default: fixed
units/work/duration. I understand what they mean though.
Right now, I'm thinking I want Fixed work, rather than
the default fixed units, because {most times}, a single
task will take x long regardless of number of people...at
the same time, I'm thinking fixed unit might be ok for me
also...except that when I have it on Fixed units, I am
unable to make the [Work] un-tied from [Duration] since
i'm using Work as the time I estimate the resource to
complete the task, and Duration as the timeframe in which
it will be completed...Is this the right use? am I
getting my terms right?
2. In general, should I just use Work (for time-fram
resource is expected to complete work), Duration for
timeframe in which it's expected to be completed, Never
touch Start and Finish - leave that to auto-update: when
I do resource leveling or when a successor task gets done
ahead of time, use Priority to somewhat control resource
leveling (I'm using Priority,Standard -is that ok?),
3. why is it that when I go back to tasks already
entered, and I want to change the Work and Duration
columns to fix to my newly adopted definitions as-in 2
above, it doesn't allow it...I first remove the resource
name (it turns Work to 0, not sure why)...then I put the
Work value back in...give it a Duration...then put a
Resource Name back...it seems to not act right when I do
it...I'm sure it's something simple...
I know that's a lot of questions, probably all newbie
too...responses to any of the items above will be
helpful...or direction to some URLs that can help.
Thanks a lot.
Just a quick question (I hope)...I'm just starting out at
this, and I want to know what you guys recommend. My
team develops custom software. We will be using Project
2003 and PWA. My question is:
1.
I'm a little confused which one I want as default: fixed
units/work/duration. I understand what they mean though.
Right now, I'm thinking I want Fixed work, rather than
the default fixed units, because {most times}, a single
task will take x long regardless of number of people...at
the same time, I'm thinking fixed unit might be ok for me
also...except that when I have it on Fixed units, I am
unable to make the [Work] un-tied from [Duration] since
i'm using Work as the time I estimate the resource to
complete the task, and Duration as the timeframe in which
it will be completed...Is this the right use? am I
getting my terms right?
2. In general, should I just use Work (for time-fram
resource is expected to complete work), Duration for
timeframe in which it's expected to be completed, Never
touch Start and Finish - leave that to auto-update: when
I do resource leveling or when a successor task gets done
ahead of time, use Priority to somewhat control resource
leveling (I'm using Priority,Standard -is that ok?),
3. why is it that when I go back to tasks already
entered, and I want to change the Work and Duration
columns to fix to my newly adopted definitions as-in 2
above, it doesn't allow it...I first remove the resource
name (it turns Work to 0, not sure why)...then I put the
Work value back in...give it a Duration...then put a
Resource Name back...it seems to not act right when I do
it...I'm sure it's something simple...
I know that's a lot of questions, probably all newbie
too...responses to any of the items above will be
helpful...or direction to some URLs that can help.
Thanks a lot.