Better to define traffic light indicators at TASK or PROJECT LEVEL?

A

anovak

For some reason I though you could define them at the task level and
roll them up some way. mmmm....so they would be maintained in both
places then.
 
D

Dale Howard [MVP]

Andy --

Create both project and task formulas using stoplight indicators. After you
create one of them, you can import both the formula and the stoplight
indicator criteria into the other one. Hope this helps.
 