Exactly what I thought. I had changed the global project start
date
previously and it didn't affect any projects negatively.
However, now I have a different problem as a result of having
changed my
global calendar from 8 hours to 7 hours. We are mid-stream in a
number of
projects, and now the durations for tasks are off. Is there any
way to
correct this with minimal headache?
thanks -
Naomi
:
Hello Naomi,
You're welcome for the help and thanks for the feedback.
To your latest question -- I assume you are referring to the
Project
start date set in the template you are using. When you create a
new
project based on the template, one of the first things you will do
is
change the start date for the newly created project. That changes
the
start date *only* for the new project, it will have no impact on
any
other project files. Changing the start date of the template file
will
also have no impact on any older projects, just new ones you
create from
that time forward.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
Hi Julie, thanks for your answers. I fiddled with a number of
the
settings,
turned on the times, and found buried in Project Information,
Enterprise
Global, the hours were 12 hours off. As it's 3:21 pm now it was
reading as
12 hours later, or 3:21 am tomorrow. Have NO idea how that was
set.
Question: the project information also shows a default project
start
date of
May xx 2002. If I update that, will it throw off all the
projects I
have
online now?
Thanks again for your help, you're very thorough and clear!
Naomi
:
Hi Naomin,
My comments/questions are inline.
Hi Julie,
This is Project 2003. The first task does not have a
constraint
but
as soon
as I try to change the date from 7/17 to 7/16, the constraint
applies
itself.
How are you trying to change the date? If you type in a date
in the
start field, *you* are applying the constraint.
I don't know where to see start times; far as I know we never
formatted for
that.
Tools > Options, View tab. Select a date format showing date
and
time.
Even though you have never seen the times, they are always
there --
Project calculated to the minute level.
It's very bizarre. I did find a customized enterprise field
that was
applied to the enterprise table indicating a start date which
for
some
reason
was still picking up the 17th, so I deleted that field,
saved,
closed
project
and reopened the problem project. Still there.
What do you mean when you say you deleted the field? Removing
the
field
from the table does *not* delete data. Is it possible the
enterprise
field you removed was an actual start date?
In fact, just now recreating yet another project, I see that
all
the
dates
are picking up TOMORROW. So there's a problem with the
calendar
somewhere.
I did change the global calendar to read from 9am to 5pm
across the
board by
selecting all the days of the week for all time; they now
have
hatchmarks
indicating the change. Could it be that?
I assume you are working with Project Server as you mention a
customized
enterprise field. Can you check with the Project Server
administrator
and have him/her check the Enterprise Global calendar? Is it
possible
the Enterprise Global calendar has July 16th set as a
non-working
day?
Julie
Thanks!
Naomi
:
Hello Naomi,
What version of Project? What is the start time for the
Project
on
July
16th? Does the first task in the project have a start no
earlier
than
constraint?
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information
about Microsoft Project
I am writing a new project that refuses to accept a start
date of
Monday,
July 16th. It automatically slides over to July 17th.
The
project
information box indicates the 16th but the table won't
take that
date.
The
global calendar has no restrictions on that date. I've
tried to
recreate the
project, by copying all the tasks and dumping them
straight into
a
blank
template and I get the same thing. The resource assigned
to the
beginning
task also has no restrictions in his calendar. Any clues?
Thanks!
Naomi